Piling starts in English Street (Site 12)

October 20th 2010 - Pile driver on Site 12
On Wednesday this week, the gear arrived for piling works on Site 12 in English Street - right next to Beckley House. 

We wonder how many residents knew what was going to be happening right outside their windows?

What is Piling ?

Piling is the term used to describe the process of driving piles into the ground to create deep foundations.
No construction work will be possible on Site 12 until such time as the site contamination and remediation plan has been scrutinised by Planning and signed off.  The deadline for this application is 1st November 2010.


Wednesday, 14 July 2010

Highways #2: This parking bay is NOT suspended

Yet again, MERA needs to remind EastendHomes and Telford Homes plc that NONE of the roads on the Eric & Treby Estate are Estate Roads

Site 12 English Street: Illegal use of constructors' barriers to prevent parking 
in a Tower Hamlets Council residents only parking bay

The obstacles in the above photograph are illegal.  This is what it says on Tower Hamlets website about obstructions to roads and pavements
Obstructions to roads & pavements

It is illegal to obstruct the road. If somebody unlawfully assumes ownership of areas of a road, they are breaking the law. If a person, without lawful authority or excuse, in any way wilfully obstructs the free passage along a road, they are also guilty of an offence.

In such cases the council, as the highway authority, has legal powers to enforce their removal.
Only Tower Hamlets Council can suspend one of its own parking bays.  Suspending parking bays cannot be accomplished by a third party putting large obstacles - such as constructors' barriers in the bay. 

A parking bay is also only suspended IF it is displaying a copy of the notice citing the relevant legislation and contact details.   The only way a parking bay can be suspended at short notice is if it's for an emergency (eg a gas leak) which requires, for example, utility vehicles to attend.  Short notice suspension does NOT apply to planned building works.

The Tower Hamlets website also says

Any building materials that block the pavement cause an obstruction to pedestrians, and are potentially dangerous. If you encounter any of the following problems please report them using our online form:
  • skips / scaffolding / advertising boards blocking the pavement
  • no barriers around street works / roadworks
  • banners or bunting causing an obstruction, or
  • any other building materials blocking the pavement, or building work that is endangering pedestrians.
Hoarding has been erected without any display of the required licence and without any consultation with residents and tenants as to the impact on local people including those with disabilities.

All works on the Eric & Treby Street site should proceed according to a shedule which should provide adequate time to apply for the appropriate licence and communicate with residents as to what is planned - allowing sufficient time for residents to make comments and plans to be revised accordingly.

Construction Management Plan and Consultation with Local Residents

One of the reasons why the Construction Management Plan was REFUSED was because of the inadequate consideration given to the management of site traffic, the separation of pedestrian routes from the site works and the general health and safety of local residents.  MERA has been highlighting causes for concern to Planning every week.

Planning have confirmed to MERA that EastendHomes agents need to submit another Construction and Management Plan for approval BEFORE any works above ground can commence on ANY of the sites.

Such a plan will be subject to consultation with residents.

MERA will be encouraging residents to write in and comment on the handling of matters relating to site traffic, parking bays and pavements during the consultation period.  

It's also very likely that we will also submit a petition - so watch this space!

IF YOU SEE CONTRACTORS OBSTRUCTING ROADS OR PAVEMENTS 
PLEASE CONTACT MERA ON THE MERA HOTLINE No 
(talk or text) 07932 626340

Highways / Traffic Management - see also:

Friday, 9 July 2010

MERA is now watching Site 12 in English Street

EastendHomes propose to create four affordable homes (3 beds x 5 persons) on the land adjacent to Beckley House and 2-26 English Street.  This is known as Site 12 within the Eric and Treby Street Estate redevelopment.

Yesterday Telford Homes plc were busy erecting the posts for the site hoarding - see the photo below.  As you can see they clearly come to the edge of the pavement which means that there are obviously plans to STOP residents from walking along that part of the pavement.


Now to have hoarding which disrupts pedestrian flows you need to have a Hoarding Licence. The Site Manager asserts that they have one and will be displaying it in full view when the hoarding has been erected
Our priority is to have a safe neighbourhood for the duration of the redevelopment contract.  In particular to make sure that the site is SUPER-SAFE for children during the upcoming school holidays.  
Consequently MERA is:
  • checking with Tower Hamlets Council what plans have been submitted for compliance with the conditions for having site hoarding and the movement of pedestrians including children
  • checking with the Highways department whether there have been any proposals to suspend the parking bays immediately outside the site to create a pedestrian walkway for those people
  • expecting that ALL provision for the separation of site traffic from pedestrian traffic complies with requirements to make the public highway accessible for disabled persons who need carriageway crossovers to get up and down pavements.
The Council's website clearly states the following
Scaffolding and hoarding licence

When carrying out any building work, maintenance, or removing part of a property next to a public road, pavement or rear lane, the safety of people on the road is paramount.

You must provide safe areas at ground level or a platform at high levels. When it is necessary to place hoardings on the road/pavement around the place of work or scaffolding, you need to obtain permission from the council by completing a form together with a sketch. If you get permission, please read it carefully and make sure you adhere to all the conditions of the licence.

Basic requirements

Hoardings:
  • Must be a minimum of 2.5 metres high and able to withstand high winds
  • Must have illumination
  • Must have a smooth finish with no protruding parts
  • Must have pedestrian walkways of satisfactory width maintained or provided, and regularly inspected by the contractor
Lighting:
  • Baulk timbers must be illuminated along their upper surfaces by red lights set at intervals no greater than 3 metres.
  • A hoarding that is on the carriageway – or is 45cm or less from the kerb face – shall be illuminated by red lights set at intervals no greater than 3 metres. The lights shall be positioned at a height of approximately 1.8 metres.
  • A hoarding which forms one side of a temporary walkway or one side of a stretch of unenclosed footway shall be illuminated by white lights set at intervals no greater than 3 metres.
We note that all work stopped after we pointed out the requirements for lighting.......

The critical issue of course is that there SHOULD be NO CONSTRUCTION OR DEVELOPMENT on this site UNTIL  the Construction Management Plan and ALL other pre-commencement planning conditions have been formally approved by the Council.

We've received professional advice that to do otherwise would invalidate the Planning Permission which would, of course, mean it would have to be applied for all over again.

The fact that the Construction Management Plan was REFUSED (see Decision Notice - REFUSED (8 June 2010) Delegated Report on reasons for refusal) means that it has to be formally resubmitted and consulted upon again.
  • We have some very scathing remarks to make about the inadequacies of the Construction Management Traffic Plan which was submitted AFTER the consultation period started for the last application.
  • We've also been talking with managers in the Health and Safety Executive's London Office this week and will be elaborating on the deficits in site traffic management on this construction site on a blog post next week.
To date, there has been no resubmission of a Construction Management Plan.

So nothing is going to be happening in terms of building of in Site 12 (or any of the other sites on the Eric & Treby Estate) any time soon.