Saturday, 23 October 2010

Piling starts in English Street (Site 12)

October 20th 2010 - Pile driver on Site 12
On Wednesday this week, the gear arrived for piling works on Site 12 in English Street - right next to Beckley House. 

We wonder how many residents knew what was going to be happening right outside their windows?

What is Piling ?

Piling is the term used to describe the process of driving piles into the ground to create deep foundations.
No construction work will be possible on Site 12 until such time as the site contamination and remediation plan has been scrutinised by Planning and signed off.  The deadline for this application is 1st November 2010.


Sunday, 12 September 2010

Site 14: Site contamination and remediation - our comments

The process for investigating the extent of site contamination on the Eric & Treby Estate and making proposals for how it should be dealt with continues.

Tower Hamlets Planning have recently agreed that:
  • (Stage 1 Desk Research) the report commissioned by Telford Homes from Herts and Essex Site Investigations has satisfied the Stage 1 requirements of Planning Condition 3 relating to the investigation of site contamination on the land included in proposals for the Eric & Treby development
  • Stages 2 (Site Investigation) and Stage 3 (Site Remediation):  Approval is now required for all proposals for site investigation; the results of investigation must be produced and the plan of remediation approved IN ADVANCE OF DEVELOPMENT on:
    • EACH individual numbered area of site development and
    • EACH numbered area of landscaping strategy

It's important to note that NO CONSTRUCTION WORK CAN COMMENCE ON SITE UNTIL PROPOSALS RELATING TO THIS PLANNING CONDITION FOR THAT SITE HAVE BEEN APPROVED

To date Telford Homes have submitted an application for approval of details to satisfy Planning Condition 3 for ONE site only.

The site in question is Site 14 on the corner of Eric Street and Ropery Street.

This is the site which was closed down after the investigation by Planning Enforcement found that Telford Homes had proceeded to commence construction and thus had breached both the planning permission and the terms of the Planning Condition 3 relating to site remediation works

On Friday MERA submitted its comments on PA/10/01560 - Application for Approval of Details re Site 14 ONLY.

Here's a summary of the points made:

Overview
We remain very seriously concerned about Telford Homes' approach and attitude to health and safety regulations and requirements and general duty of care owed to others - which have been repeatedly disregarded to date. 

Site Investigation:

BREACH OF PLANNING PERMISSION AND PLANNING CONDITION 3
  • We noted that the site was only properly investigated AFTER the foundations had been dug and pipes laidie in breach of planning permission / planning condition 3
SITE CONTAMINATION
  • We are pleased to see that it is now being fully recognised that the identified contaminants are prevalent across the site including those sites not properly tested previously - such as Site 14.
Site Remediation

PROTECTIVE CLOTHING
  • We have not seen any evidence that workmen were using appropriate protective clothing in relation to the contamination while working on Site 14  (as opposed to general protective clothing used on all construction sites)
Site 14: No protective clothing re soil contamination
    REMOVAL OF SOIL / SOIL CERTIFICATION

    • We don't understand why we are now seeing different depths proposed for the removal of soil compared to the original report from the same firm. We expect to see 0.5 metre of soil removed from ALL communal landscaped areas - as per the original report on this topic and 0.9 metres of soil in areas of private gardens
    • We suspect the developer is in some difficulty in connection with certifying the soils which have already been removed from the site and we doubt very much whether these can now be identified.  We suspect they have already been mixed with other soils or already removed from the site altogether - as has happened with soil removed from Open Space 2.

    Site 14 - Where's all the soil gone?
    Was it certified before it left the site?
    What do you think?

    WASHING/CLEANING PRIOR TO LEAVING SITE: 
    • The Decontamination proposals relating to Site 14 are completely inadequate.  The workforce need to be decontaminated BEFORE they leave site 14 NOT before they leave the Eric & Treby Estate.
    Do we have to make the point yet again that this is a residential estate with a high proportion of families with small children - many of whom play on the streets?  


    It is ESSENTIAL that no contaminating material finds its way on to the streets or pavements. 
    • How exactly do the workforce get from Site 14 to the washing and cleaning facilities at the site office?
    • How exactly does Telford Home prevent contaminants from the site transferring via boots and clothing to the streets and pavements? 
    • Are workers going to be taken back to the Site Office in a vehicle?  This needs to be made clear.
    We expect the scheme to be compatible with the standards listed in INFO-PM2    Key Information Sources : Project Management – Health and Safety and Quality Management on page 188 of Model Procedures for the Management of Contaminated Land  
    ENVIRONMENTAL MONITORING AND CONTROLS
    • We visited the site on a number of occasions and there has been no evidence to date of damping down of dust generation caused by the excavation or regard for people living near the site.  
    Eric & Treby - Site 14 (Eric Street):  the latest play structures
    very large unattended vehicles for children to play on
    plus contaminated soil which is not covered
      TRAFFIC MANAGEMENT PLAN
      • A Traffic Management Plan exists for this site but is not included with this application.  As stated the traffic management plan is inadequate as it fails to be sufficiently specific as to streets and flows and specific places where lorries will be queued. 
      • A key concern in relation to this site has been the construction vehicles parked unattended on the street where they are accessible to children - we have witnessed workmen on the site completely oblivious to anything happening to the vehicles in the street
        If any resident has any concerns relating to the Site Investigation and/or proposals for Site Remediation please get in touch with MERA.  Details of how to contact us are included in the right hand column.


        Saturday, 4 September 2010

        Coniston House - an UPDATE

        These are the recent blog posts on MILE END RESIDENTS' NEWS about the changes to the open space in the area surrounded by Coniston House - and an update about the outcome.

        Open Space development at Coniston House (Open Space 2) as at 1st July 2010
        These are the previous posts about the sudden enclosure and tarmacing of open space and removal of too little soil without proper precautions being observed in relation to the soil contamination:
        In response to the petition by Coniston House residents and the representations MERA made to the Council's Planning Enforcement Officers MERA received a letter from Owen Whalley Head of Planning and Building Control.  

        In summary:
        • Eastend Homes says the tarmac area is temporary and will be remediated and reinstated when construction works are complete
        • Eastend Homes MUST submit an application for temporary planning permission in order for the Council to obtain local residents views and determine if the car parking arrangements are acceptable and
        • issues re dust from the contaminated soil have been referred to Environmental Health
        This is the relevant extract.  Right click the image to see a larger version.

        Letter from Owen Whalley, Head of Planning and Development Control 28th July 2010
        This page on the Council's website is where all the applications for planning permission re. the Eric and Treby Estate can be found.  This includes all applications for approval of details relating to satisfying planning conditions.

        You can also check the latest status of all planning applications on our Redevelopment Page which tells you what is permited, what has been refused and what is "in progress" plus deadlines for all comments .


        Thursday, 2 September 2010

        Telford Homes need to think again about traffic management

        Below MERA demonstrates why Telford Homes need to think again and come up with a more effective traffic management plan for the construction traffic trying to access and move around EastendHomes' Eric & Treby Estate.

        A Very Tight Turn #1 - 1st September 2001
        a 4 axle HGV truck took 5 goes to exit from Site 4 via Tony Cannell Mews
        there is no indication of any suspended parking bays 

        in the Construction Management Plan version 2
        Yesterday a 4 axle HGV was spotted trying to exit the car park next to Coniston House which serves as the access route to open space 2 and the unauthorised storage compound to the rear of site 4. 

        The truck needed to reverse five time to negotiate the turn. Fortunately a banksman was present to assist.

        According to the driver of the truck if the parking space on the left closest to the turning was suspended the turn would be possible. All cars were parked correctly in designated parking bays. There is no indication that this bay should be suspended in the Construction Management Plan.

        EastendHomes Boss Paul Bloss told MERA earlier this summer that the largest trucks would only access the larger roads and that vehicles would be down-sized for use on more narrow roads.  We think he should come down to the site and see for himself what's going on.  In the meantime we will continue to photograph vehicles getting into trouble - and will send these photos to Planning.

        How local people help with traffic management of construction traffic

        Another local resident commented to Tower Hamlets about the traffic management on the Estate as part of the Consultation on the Revised Construction Management Plan (part of planning condition 5)
        Personally I have seen a ‘normal’ woman guide a cement mixer truck out of Tony Cannel Mews, i.e. she was not wearing hi vis jacket. It COULD of course have been the case that she was in fact the banksman and that her jacket was in the truck/bag/under her jacket…It COULD also be the case that she was just a friendly passer by taking it on herself to help the driver of the truck. Anyhow, what I saw was not right. It is my further observation though that the use of banksmen is much improved on the site.

        MERA comments on traffic management on Eric & Treby Estate

        Yesterday MERA submitted detailed comments to Tower Hamlets Council about various aspects of the Construction Management Plan.  Our 30 page schedule of detailed comments included various points about traffic management

        These included the following:

        • The Plan proposes various Traffic route plans for numbered construction sites which are either INCORRECT, NON-EXISTENT or propose DANGEROUS practices - impacting on the wider population and health and safety of pedestrians (adults and children), disabled people, cyclists, motor cyclists and drivers.  
        • Traffic routes are factually incorrect.  They provide route directions for site access which contravene current highway regulations for this area
        • The construction traffic route for site 7 is non-existent.  
        • The Plan FAILS to provide traffic route plans and instructions for nine  numbered open spaces requiring landscaping.  These are part of this development, will require construction traffic to attend and remove existing soil and landscaping and bring in new materials.  The MISSING route plans all need to reflect the changes in locations of site stores as this development nears completion.
        • Contradictory statements are made about the use of banksmen on site. 
        • Major confusion about what is meant by the term "site access" (ie does this mean the Estate or the 15 individual numbered construction sites and the 9 numbered landscaping sites?)
        • Lack of any plan indicating which roads are suitable for different sized vehicles.  HGVs which are too big are trying to access roads which are too narrow
        • Loading and unloading bays are not apparent on all route plans where this needs to take place in the street
        • No indications of any planned road closures to bring in and take out cranes, concret crushers and any other heavy machinery related to the construction
        • Inadequate indication of how construction and pedestrian traffic will be separated at specific sites
        • Inadequate recognition of the constraints of the red route regulations along the A11
        • Inadequate recognition of high risk areas re movement of people with disabilities through the site
        • Inadequate recognition of high risk areas where children play (without supervision)
        • Unclear as to how and where all vehicles leaving "the site" (whatever is meant by this term) have their wheels washed to avoid distributing contaminated soil onto the road network - particularly the LOCAL road network within the estate
        • Sweeping roads to remove dirt from the sites is unsatisfactory if the soil is contaminated as this just results in air-borne dispersion of the contaminants.  There needs to be more emphasis on sucking muck on the roads within the estate.
        These are just a small part of our comments!

        MERA has asked Tower Hamlets Planning that permission to approve the details in the Construction Management Plan be REFUSED.

        A Very Tight Turn #2  2nd September 2010
        a 4 axle HGV truck trying to exit from Site 12 (English Street) 
        there is no indication of any suspended parking bays opposite the site entrance
        in the Construction Management Plan version 2



        Thursday, 22 July 2010

        Top 10 Problems with the Kerrygold Garden

        Open Space 3, which contains the Kerrygold Garden, has a large number of problems which are summarised below.

        MERA started out at the beginning of this week talking with local residents who were very annoyed that the garden had been "closed" making it necessary for them to move The Big Lunch from the Recipe Street Garden to the strip of grass at the edge of Eric Street (see The Big Sunday Lunch moved).  Towards the end of the week, we're now very clear that there are a significant number of problems with this development.

        We've listed them below.
        1. Unlawful Development:  Before any of the development can start, the architects and developers acting on behalf of EastendHomes have to satisfy the planners about a number of different planning conditions.  This development went ahead despite the fact that these conditions had not been satisfied.  The site has therefore been closed because of its unlawful development in advance of the provision of information which is required to satisfy all the pre-commencement planning conditions.  
        Breach of Condition 11 (Landscaping Strategy and Management Plan)
        A site visit revealed that Open Space 3 has been completed, including landscaping, prior to this condition being formally discharged.
        Planning Enforcement Letter
        1. Not developed according to permitted design - Somebody somewhere missed the point.  You don't go to the trouble of seeking planning permission and get designs approved so that you can then go and do the development according to a completely different design.  Permission is for the design specified in the drawing submitted with the planning application and that's all.  If you want to do something different you have to submit a revised design and get formal approval - which also requires formal consultation with local residents.
        2. No formal consultation on the revised design - There's no problem about revising a design so long as you give ALL the relevant people the opportunity to comment on it.  Consultation is NOT the Project Manager asking a few people whether they agree the development should go ahead.  Formal consultation is done by the Council's Planning Department who have to ensure that everybody who needs to know has been informed. This did not happen.  Read the repurcussions in the next post.
        3. MAJOR loss of amenity - due to excessive noise at night.  This week MERA has had to write to Planning to advise them about a major complaint by local residents.  The open space is now being used all night long by young men who are congregating there in groups and making a significant noise.  Residents are now finding it very difficult to sleep at night.  Residents are also very disappointed that the Safe Neighbourhood Team have done absolutely nothing to address this issue despite the fact that a Dispersal Zone is in place which includes this garden.  Recently residents chose to spend money allocated to the area for improvement - on removing the brick walls which the men used to sit on.  These were replaced with fences so the young men have moved to the tables and chairs in the garden.  The Crime Prevention Officer is very clear there should be nowhere for young men to sit.  Residents will be making representations on this issue to the Safe Neighbourhood Team at its meeting next week.  The point is the design should be designing out activities with a negative impact on local amenity rather than increasing problems for residents!!!
        4. Significant loss of green open space - A very significant amount of green open space for the children to play on has been lost because the car parking area is now a lot bigger than the permitted area.  Yet again we appear to have developers who make it up as they go along. If you compare area of parking on the plan to the area of parking in reality, you'll see very quickly that the space allocated to parking has grown very significantly.  It should be about 25% of the site and instead it's more like 40% of the site
        "I've yet to see a builder with a plan in his hand"
        Chair of MERA

        Council Approved Design for Open Space 3 - between Eric Street and Windermere House
        1. Unlawful materials used.  When Councillors were approving this application, one of the points they made to residents was that they were NOT going to allow open space to be reduced unless very high quality landscaping was used on the remaining areas of open space.  They gave permission for high quality materials.  The developers have substituted with cheaper materials.  MERA has complained and EastendHomes have been told that the specified materials need to be used.  The tarmac should be removed before the development is completed and MUST be removed before all homes can be occupied (see Planning Condition 11 - Landscaping Strategy & Management Plan)
        1. Site drainage has been affected - By substituting tarmac for the approved pavoirs, the ratio of permeable (water can go through) to impermeable (water sits on top) materials has been changed.  Increasing impermeable materials increases the puddles and the risk of flash floods during heavy rain.One of the reasons why there is now more flooding around the country is because more and more people have paved their gardens and the water has nowhere to go   Consequently the Council seeks the use of permeable materials whereever possible eg car parking areas and permeable materials were what it had approved.
        Breach of Condition 3: Site Contamination
        After conducting a site visit it is apparent that Open Space 3 has been completed and foundations have been laid at Site 14, prior to Condition 3 having been formally discharged.  I have advised the developers that Open Space 3 and site 14 must be closed
        Planning Enforcement Letter


         Extract from 1895 OS Map showing Rope and Twinery Works on Open Space 3 and 4
        1. Site Contamination:  We have identified from maps that the majority of Open Space 3 (and 4) used to be part of a Ropery and Twine Works. This part of the site includes all the locations where the arsenic, lead and nickel were found in the previous tests as well as the carcinogenic polyaromatic hydrocarbons which are found throughout the Eric & Treby Estate. The results of tests done by Herts & Essex Site Investigations (summarised on Appendix 1 Site Plans and Conceptual Model/Sheet 7 March 2010) very clearly indicate that Open Space 3 is the most contaminated part of the whole site.  In other words
          • no amount of additional testing is going to eliminate the EXPERT tests already done in March which identified the presence of Arsenice produced the recommendation that 0.5 metres of soil needed to be removed
          • None of these tests can be ignored when making an assessment about this site and reviewing the recommendations of the experts as set out in the report which has already been submitted to the Council in relation to the approval of details relating to site contamination/site remediation.  
        2. Poor Garden Maintenance:  Residents have commented to MERA that the plants are not being watered properly during the hot weather.  Expert opinion suggests that some of the plants have "bolted" because of the lack of water.
        3. EastendHomes doesn't have a very good track record when it comes to open space and places for children to play - (see British Street: Children must not play on this site!).  See above.
        It's very depressing making lists like this - because this is the first part of the (unlawful) development and just look at how many things they've got wrong!

        Hopefully by highlighting the issues we can get this changed as development proceeds on Eric & Treby.


        If you want to be kept updated why not subscribe to this blog.  
        You can do this by clicking the link below 
          Subscribe to MERA - Mile End Residents Association Blog by Email

        Monday, 12 July 2010

        A Petition from Coniston House residents

        Members of Mile End Residents Association who live in Coniston House - on Eastendhomes' Eric and Treby Street Estate - are today sending a petition to:
        • Owen Whalley, Head of Planning and Development Control at Tower Hamlets Council and 
        • Ted Wojewodka, Manager - Complaints Team (London) Health and Safety Executive.
        [Update 12th July 2010: We've received a very prompt written response from Owen Whalley, promising to look into this matter]
           The petition results from:
          • the recent excavation of the grass and soil and tarmaccing of "Open Space 2" (the space in the middle of the Coniston House blocks), part of the Eric & Treby Street development - with no prior notice and no notified indication of why it is there
          • the lack of any indication in the draft Construction Management Plan of any works in this area other than those relating to the redevelopment of the Open Space for recreational purposes.
          • the general lack of any attention to health and safety issues on this site by the contractor Telford Homes plc
          • the breach of planning permission and planning conditions
          • the generally very poor level of communication with residents
          • the total lack of notification to residents of Coniston House of any works in their area and the timing of works (eg the development of the undercroft; the development of the open space). 


          The petition states the following:
          The car park at Coniston House has been extended during the first week of July.  This was not part of the building plans that were approved by the Council, which showed the area as part car park and part play ground.  The car park now encroaches on the space that was planned to be used as a playground.  Residents were not informed or consulted about the change.

          Residents are also concerned that site traffic is going the wrong way around the site and construction trucks are manoeuvering without banksmen to ensure the safety of pedestrians and other road users

          We demand that the works are changed back to the original plans and that residents are consulted about any future work in this area.
          83% of the properties signed and 100% of those who were asked.  There are 66 properties in the block.  The petition includes 56 signatures from 55 properties .  Those who have not signed were out when the local block representative visited their home.  Nobody refused to sign.
            
          What do local residents think?  

          Residents made the following points when signing the petition

          • Residents generally commented about the total lack of any notification about what was happening and the overall level of noise
          • Nobody notified a lady who is asthmatic.  She was very upset by the development as the dust really affected her asthma and she wasn't given any warning.
          • Many residents do not know about the new 1 bed flats to go in the undercroft area of Coniston House
          • Many families had been looking forward to having a Play Area next to Coniston House as Mile End Park is too far away across a busy road.  They are upset that the grass has been taken.  The grass is used including for dog walking.
          • The railings block access from the car park to the main block doors. One one you have to fight through a tree in order to get through
          • In the absence of any communication from EastendHomes or Telford Homes, people think the tarmac will be used for car parking spaces.  They commented that there are plenty of empty car parking spaces.  Residents do not feel that there is any need for any more.

          Contaminated soil extracted: Residents were also not aware that the site which was excavated was contaminated ground and that the soil excavated required controls attached to its excavation which were not evident to any of those who watched the excavation.

          Site traffic breaching planning conditions:  We have already commented to both the Council and the Health and Safety Executive (responsible for construction sites) about the complete disregard for local residents demonstrated by drivers of the HGV vehicles taking away the soil (see MERA Blog Eric & Treby Site Traffic "out of control").  We also saw no evidence of any the health and safety measures identified in the plans submitted to date - even though these are not, as yet, approved.

          CLEARLY THE AMENITY AND THE HEALTH AND SAFETY OF LOCAL RESIDENTS HAVE BEEN AFFECTED BY THIS DEVELOPMENT

          It is INTOLERABLE (and maybe illegal?) for buildings works to be taking place:
          • in the absence of a construction management plan approved by Tower Hamlets Council - See MERA blog posts Construction Management Plan - REFUSED and WHY the Eric & Treby Construction Management Plan was refused
          • in the absence of an approved site contamination/remediation plan - for a Development Site which has been identified by experts as being contaminated with Arsenic, Nickel, Lead and poly-aromatic hydrocarbons - see MERA Blog Post Eric & Treby Estate: Site Contamination
          • in the absence of any measures to reduce dust and its impact on people living nearby with respiratory problems such as asthma
          • in the absence of satisfactory measures to comply with the details of all other pre-commencement planning conditions
          So far as we are aware Tower Hamlets Council has a statutory duty of care towards the residents of this borough which involves exercising such powers as it has under planning and health and safety legislation to ensure that residents are NOT exposed to undue and avoidable risks.  That, as we understand, forms the basis for many of the terms of the planning permission and planning conditions which are currently being ignored.

          WHAT MERA WANTS TO SEE HAPPEN

          We want the statutory agencies to make sure that:
          • all work on this site is STOPPED until such time as ALL appropriate pre-commencement planning conditions have been satisfied. 
          • the construction management plan (when finally approved) includes detailed/stipulated arrangements for communicating explicitly and promptly with ALL tenants - at all stages of this development - as and when required (ie BEFORE works start)
          • all health and safety aspects of this development are comprehensively addressed - by Telford Homes plc and Eastend Homes in liason with Tower Hamlets Council and the HSE London Team responsible for construction sites
          • the construction management plan and all other plans which relate to the creation of dust MUST create an environment which does not jeopardise the health of people living nearby who have serious respiratory problems.  This is particularly important given the fact the site is contaminated and includes carcinogenic material. It is not acceptable to excavate soil without precautions and/or create a development which could lead to people having their health put at risk, leading them to being admitted to hospital or worse.  The site must be SAFE for those with respiratory/disability problems.
          • Everybody responsible for the development of this site MUST have a complete and accurate appreciation of the dangers of dust for those with respiratory problems and act accordingly.  Otherwise they render themselves liable to prosecution.  Ignorance is not a defence in law for developments such as this.
          Note: The covering letter with the petition is being copied to:

          • Councillor Rachael Saunders, Cabinet Lead for Health and Wellbeing (and Councillor for Mile End East)
          • Councillor Tim Archer, Scrutiny Lead for Healthy Communities and Chair of the Health Scrutiny Panel
          • Martin Young  Chair EastendHomes
          • Paul Bloss CEO EastendHomes
          • Andy Osborne, Project Manager, EastendHomes
          • Stephen Irvine, Development Control Manager
          • Richard Murrell, Planning Officer - The Eric & Treby Estate
          • Cain Duncan, Planning Investigation & Enforcement

          Thursday, 1 July 2010

          MERA Comments on Site Ecology Application

          The large mature Lime Tree not mentioned in the Habitat Survey 
          which crosses the boundary of Site 10 - above and beneath the ground

          Below you can find the summary of our comments in the covering letter to Mile End Residents Assocation's formal and detailed written response to PA/10/01121 - Approval of Details - Site ecology - pursuant to Condition 25 (Site Ecology) (ref the planning conditions relating to the permitted development on the Eric & Treby Estate ref: PA/09/2065)
          There are a number of problems with these proposals.

          The first problem is that yet again the Scheme Proposals appear to be incomplete as the Habitat Survey does not appear to have actually surveyed Site 10.  On this basis alone we feel the Scheme should be refused, revised and resubmitted AFTER Site 10 has been surveyed properly and precise recommendations developed for this site.

          Other concerns include:
          • there has been no survey of the lime tree at 648 Mile End Road which overhangs Site 10 re a number of matters eg no survey of nesting birds, no mapping of area of site 10 covered by roots of a healthy mature tree, how to deal with site contamination while protecting the root ball etc
          • much more precise recommendation are required re protection of the Lime Tree at 648 Mile End Road and its maintenance as a mature healthy tree given the need to also address the site contamination in the gardens of site 10
          • Site 10 needs to be surveyed for bat roosts. 
          • we'd like to see more specific proposals for planting trees in/around the site and Hamlets Way/Southern Grove
           Please note that we are using our website, (http://www.mile-end-residents.co.uk)  blog (http://meracouk.blogspot.com/) and Flickr account (http://www.flickr.com/photos/mile_end_residents/) for updates, comments and photographic records for the duration of the contract. 
          There is a significant amount of other documentation which still needs to be completed, submitted, consulted upon and addressed  (eg Construction Management Plan, Site Delivery and Services Plan, Landscaping strategy and management plan, refuse and recycling storage plan, energy efficiency scheme) we suggest there is plenty of time to remedy the deficits in terms of the surveys which have, as yet, not been conducted on Site 10.

          The report recommends:
          • a bat survey - the maisonettes at 1-14 Brokesley Street have been empty for some time and residents have seen bats in Brokesley Street in the past
          • a survey of nesting birds within the dense canopy of leaves.  
          Nesting birds are protected by law during the nesting season. 

          Wednesday, 30 June 2010

          MERA comments on Site Remediation Application (and more news!)

          Below you can find the summary of our comments in the covering letter to Mile End Residents Assocation's formal and detailed written response to PA/10/01093 - Approval of Details - Site Remediation (ref the planning conditions relating to the permitted development on the Eric & Treby Estate ref: PA/09/2065)
          We are becoming more and more concerned about what appears to be a sloppy approach to the developments of both plans to discharge the planning conditions and site practices.

          There are a number of problems with these proposals

          Scheme Proposals for investigation and remediation of site contamination are incomplete - they completely ignore site 10.  On this basis alone we feel the Scheme should be refused, revised and resubmitted.

          However other concerns include:
          • Site 3 has been "completed" and reopened without the recommended remediation works (ie no excavation of soil to an appropriate depth prior to replacement). 
          • The management of the Eric & Treby site also failed to inform other relevant agencies about the fact that Site 3 was being assessed for site contamination - contrary to recommended practice
          • Decontamination arrangements take no account of the dispersed nature of the various sites of soft landscaping where remedial works are required and make no provision for the protection of the public as the workers walk in their protective clothing across the estate to the area where they can clean up!
          • The traffic management plan is incorrect
          • Details of how noise will be suppressed are not as detailed as in the Construction Managament Plan
          Please note that we are using our website, (http://www.mile-end-residents.co.uk)  blog (http://meracouk.blogspot.com/) and Flickr account (http://www.flickr.com/photos/mile_end_residents/) for updates, comments and photographic records for the duration of the contract. 

          At present, we are noting almost daily breaches of acceptable practice for site management.  We will be seeking enforcement action in the near future if practices are not remedied immediately.
          We now wait to hear what is the response from Tower Hamlets Planning

          Site 2: Excavation of contaminated soil

          However we did think it might be sensible to include a couple of examples of what we mean by sloppy practices.

          Excavation of contamined soil on Site 2 (behind Coniston House)
          BEFORE this is a permitted development
          photo copyright MERA - some rights reserved.

          Just a few problems with the work to this contaminated site between Tony Cannell Mews and Coniston House!
          • soil has been excavated BEFORE this development has been permitted by Tower Hamlets Council.  Our response above is to the formal consultation on the proposed site remediation scheme scheme for dealing with the site contamination.  Until this has been agreed there can be no works on site as per the original planning permission.
          • It looks like somebody forgot to read the report from Herts and Essex Site Investigations.  They observed that the whole site is contaminated and that the soil under areas of soft landscaping need to be excavated to the recommended depth of 0.5 metres (20 inches.  The excavation did not reach the required depth of 20 inches before they started patting it down.  We estimate they have maybe excavated 5 inches - just 25% of what is required.
          • This is a contaminated site and yet there has been no communication with the residents round about.  Unsurprisingly they are very unhappy about being kept in the dark about what's going on.
          • We could see no hazard warnings or protective practices in evidence during the process of exposing this contaminated site.

          One of the requirements of the Site Remediation Scheme is that all excavation should be evidenced by photographs being taken of the measured depth of the excavation

          Just in case they forgot we thought we'd help out by taking a photograph for them!  We'll be forwarding this to planning with a link to this blog post as evidence of yet another breach of planning permission/conditions.  The kerb stones provide a neat scale for indicating depth.

          The trucks which have been on site have been engaged in all sorts of dangerous driving practices in addition to ignoring the Traffic Access Plan - which has yet to be approved.  This is what one of the MERA committee members  observed yesterday.
          Followed a construction truck out of Hamlets Way into Burdett Road this morning. I turn left down Bow Common Lane, and he was waiting in the right hand lane at the traffic lights, which is for straight on. He then decided he wanted to turn left, didn't pay any attention to me and cut me up, nearly crashing into my car despite my very angry horn honking!!! It was really dangerous and quite frightening too... he either didn't know I was there or didn't care! He then parked on Bow Common Lane near the bridge, which is also dangerous, as it is difficult to see oncoming cars when overtaking. Hopefully this is not an omen for the future!
          Response from the Head of Development Control

          In yesterday's blog post - Eric & Treby Site Traffic "out of control" - we said we were going to be asking Stephen Irvine "What exactly is the point of planning conditions if they are ignored and flouted on a daily basis? "

          Mark Taylor, Chair of Mile End Residents Association, wrote to Mr Irvine yesterday asking that question and highlighting the issues we are concerned about.

          We're very pleased to report that we received a very prompt, detailed and constructive response from Mr Irvine.  We look forward to the follow up action which was promised in the letter.

          More on this topic will be posted - watch this space!  (Meanwhile we'll keep watching the estate and construction site!)

          If you want to be kept updated why not subscribe - you can do this by clicking the link under the map and near the top of the right hand column and you will automatically receive an email copy of each blog post.

          Thursday, 24 June 2010

          Danger at Recipe Tree Garden - keep out!

          It would appear that somebody from Eastendhomes and/or Telford Homes plc has finally got the point about the state of the site contamination at the Recipe Street Garden.

          A danger sign has gone up at the fence preventing access to 
          the Recipe Tree Garden sponsored by Kerrygold Butter

          See our blog posts earlier this week which highlighted the problem which was being IGNORED by the people in charge of the Eric & Treby Street development
          It looks like the consultation with residents - scheduled to start today at the Recipe Street Garden - and BBQ will now have to happen somewhere else!

          [UPDATE:  Apparently not.  After the danger sign and fencing was removed in the morning and transported in a very unsafe way (ie unsecured and bouncing around within inches of residents' cars) away from the site, Eastendhomes proceeded to hold its consultation day as if the contamination never existed.  Of course, unless they can provide the validation photographs about excavation of existing soil and other relevant documents for the site remediation quality control, they will be unable to discharge the planning conditions and it will have to be redone.  

          In the meantime we wonder if anybody told the Kerrygold Farmers and Kerrygold Butter that they have helped to fund the landscaping of a contaminated plot.  From our perspective, while we think Kerrygold are totally brilliant for putting up the finding for community projects, we're very puzzled as to how the page on their website and the existing site contamination fits with their branding.

          For the record - PA/10/01093 - Approval of Details - Site Remediation - detailing how the site is to be remediated is with Tower Hamlets Planning at the moment and is out to consultation.  It has not been approved.  The works which have taken place technically breach the planning conditions which cover site remediation]

          Health and safety risks - not an isolated incident 

          See also British Street: Children must not play on this site.

          When is Eastendhomes going to start getting it right in the development of soft landscaping?

          It's looking more and more as if we need to call for some enforcement action from Planning so that the developers start getting it right first time - and not when residents speak up about the problems and faults.


          Reference:  Posts about Local Green Spaces

          Wednesday, 23 June 2010

          Eric & Treby Estate: Site Contamination

          The Eric & Treby Estate is contaminated.  It's not alone.  Significant areas of land in urban London in the nineteenth and early twentieth century are also contaminated because they used to be home to industries with practices which are now not allowed.

          The standards required for building land now are much higher than they used to be in the past because we now understand more about how dangerous some contaminants can be for people's health.

          This post outlines what is a complex topic.  We've had to learn about it and what follows relates to a meeting with Tower Hamlets Planning and reading the detailed reports and proposals

          Planning Conditions submission - Site Contamination

          Before any work on the site can commence - other than site investigation works - the client and contractors have to satisfy the Planners that they can meet the planning conditions.  One of these relates to investigating the contamination of the site and making good.

          The latest submission from the architects for EastendHomes to Tower Hamlets Council Planning Department, concerning the satisfaction of the planning conditions, concerns Site Contamination and Site Remediation.

          If you click the link to PA/10/01093 - Approval of Details - Site Remediation (re planning conditions relating to planning permission PA/09/2065) you can see all the evidence which is being presented to the Council about:
          • desk top analysis of previous contaminating industries on the site.
          • evidence from 36 bore holes of the soil conditions and what has been found under the ground (this also affects what sort of arrangements need to be made for foundations)
          • identification of the areas which need site remediation works
          • proposals as to how the site will be cleaned up (the Site Remediation Strategy) and what quality controls will be put in place to contain dispersal of the contamination.
          This is complex scientific area - but the evidence is there for you to see and comment on should you so wish.

          What used to be on the Eric & Treby site

          Herts and Essex Site Investigations have undertaken a survey.  They are a firm of Geotechnical and Geo-Enviromental consultants, who provide soil surveys for a wide clientele.

          Their report (Phase III Remediation Strategy) indicates that they have found widespread contamination from Arsenic, Nickel, Lead and PAF contaminated soils at the Eric & Treby Estate.

          The site history (page 4 para 1.2) recorded in the report is extremely ungrammatical which gives rise to concern as to the author's command of English in relation to reading and site investigation as well as writing.

          The report indicates (without citing the evidence found) that the site has previously been home to a Rope Works and a chemical works.  This is why Ropery Street is so called.

          This is a very likely source of the contaminants.

          The very large quantity/depth of what is essentially rubble on the site is probably due to either bomb damage (this was an area which was targeted in the Blitz of 1940) or is the rubble from the demolition of older residential properties and/or factories.


          Which are the sites which need remedial works?

          Page 18 of the Phase III Remediation Strategy provides a plan of all the areas of soft landscaping requiring works.  As you can see it's a lot of land.  There are also more detailed plans for each site showing the area requiring remediation on top of the proposed soft landscaping.

          Sites requiring remediation works



          Appendix 1 Sheet 2 shows the contamination locations - and also all the proposed sample locations which were not done and for which there is no report.
          Example:  The Recipe Street Garden - created without any remediation works - has registered Arsenic, Nickel, Lead and poly-aromatic hydrocarbons above the allowable levels identified in the Site Remediation Strategy (the latter can cause can cause cancer, mutation in and abnormal physiological development)
          What needs to be done - the Site Remediation Strategy 

          This is what the experts HESI are saying and recommending in relation to the areas of soft landscaping
          Possible site Remediation Measures
          Site Soils: 
          • Confirmation that the entire site area is contaminated and that remedial measures are required to remove risk to all areas of soft landscaping
          • Likely removal of soils within the site to remove the risk to human health
          • alter the chemical state of the site soils to reduce the impact of the end use soils on the proposed receptors
          Phase 11 Remediation Strategy - Site at Eric and Treby estates (para 2.5 page 8) 
          Soil
          The site has been classed as contaminated by Arsenic, Nickel, Lead and PAH with concentrations, whilst in place, are not significant although will require cleaning facilities and protective clothing in order to remove risk on a temporary basis to the workforce
          Site Remediation Strategy Phase III Page 9 para 3.1
          YET AGAIN(!) we have a plan which makes absolutely no reference to the protection of the public on a multi-site development within a high density residential area.

          The identified risk based on the information gained suggests that the contamination within the site is likely to cover the whole site and, as such, all areas within the site should be considered as contaminated.....The risk within the site has been identified as within areas proposed for soft landscaping where excavation of the areas should be undertaken to remove the risk to human health
          Site Remediation Strategy Phase III Page 9 para 3.1

          The Remediation Strategy is incomplete as to proposed areas requiring excavation/remediation.  Paragraph 3.2 refers to a non-existent Table 1

          Measures to remediate soil include:
          • Half a metre of soil needs to be removed under the communal areas of soft landscaping
          • 0.9 metres of soil should be removed from the area of private gardens due to the scope for people  to use the gardens to grow vegetables for eating.
          • All excavation sites will need to be photographed to provide evidence of the depth of the soil removal
          • After removal of soils, new soil will need to be imported and the quality of the imported soil will need to be tested.
          For some unknown reason no bore holes were sunk in Brokesley Street and this is not identified as a site.  In fact it's unclear whether it has even been investigated.  The area at the rear will be used for gardens and may well also need to be excavated.  We'll be commenting on this aspect in our formal comments on the planning submission and in relation to the disturbance of the roots of the very old lime tree. 

          Land Gas:  Testing is ongoing and there are no proposals as yet. 

          Foundations: The report recommends foundations of at least a metre.  This is because large parts of the site are covered by rubble.  One can speculate that this might either be due to bomb damage during the war (ie the reason why large parts of Tower Hamlets have newer housing)

          Capping is identified as an effective way of dealing with the sites which will be built on.

          Decontamination Facilities:   Washing/cleaning facilities are to be provided attached to the office facilities for all contractors and visitors.  Everybody will be required to wash and decontaminate clothing/boots before departing from the contaminated sites

          It's unclear how they get to the washing/cleaning facilities along public streets and pavements to get to the cleaning facilities for the decontamination.  Perhaps the expert advisers don't think it matters if the streets and pavements are contaminated with whatever has to be removed by cleaning? We think it does!

          Site Verification Plan:  Telford Homes are to prepare a site verification plan according to Model Procedures for the Management of Contaminated Land as required by the HESI
          It's entirely unclear whether this site verification plan has been prepared and completed prior to the opening of the Recipe Street Garden - a site identified as requiring remediation works.
          We're not happy with the cavalier approach to Site Remediation Works demonstrated to date.  Having met with the Planners last Friday, we're happy that planning conditions can contain the contamination.  However we're not happy that actions to date have complied with the proposed actions for a Remediation Strategy.  Mile End Residents Association will be making detailed comments to Tower Hamlets Planning. 

          One issue we intend to focus on is the quality control over and the validation of remediation works prior to new soft landscaping being opened to the public.  We will want to know how exactly the Recipe Street Garden has complied with the plan and, if necessary, we will be asking for an Enforcement Investigation.


          Commenting on the proposal to meet the planning condition

          MERA will be submitting a formal comment on the quality of the investigation , the report and the proposals

          You also have the right to comment if you so wish.  

          If you want to comment on the current planning submission PA/10/01093 - Approval of Details - Site Remediation you can do so by commenting online here Comment On Application or by writing to the Council

          We suggest you read the documents first

          The deadline for comments is 28th June 2010.

          If you have any queries please contact MERA
          If you have a comment please leave it below
          Email MERA with photographs of your concern

          Tuesday, 22 June 2010

          Consultation and BBQ on contaminated garden

          The invite from EastendHomes

          EastendHomes and the Mile End Estate Management Board appear to be trying to improve their abysmal reputation for dialogue and consultation with tenants/residents by having an event to "discuss the improvements to the Estate".  However the invitation appears to have overlooked a few important facts.

          EastendHomes do not listen. We can only conclude that EastendHomes suffered from complete deafness when they attended all the Strategic Development Committee meetings. 
          • In no way do residents of the Estate consider the infill developments as "improvements"!  To characterise the invitation in this way is just plain insulting.  Many tenants/residents campaigned throgh five long meetings to get the developments rejected.  Perhaps this blog needs to remind Eastendhomes about how many people signed petitions, wrote letters and regularly turned out for the meetings of the SDC at the Town Hall?
           MERA protest at the Town Hall at Mulberry Place
          • Proposed developments on the Estate - for both social housing and private sector housing - are way in excess of that indicated as at the time of the ballot.  Many residents have said that they would have never have voted for the transfer if they had known what was going to happen to their estate.
          • The replacement of kitchens and bathrooms are also NOT improvements.  The internal works more correctly have the status of maintenance because they are required by central government to bring all the housing units on the Estate up to the mandatory "Decent Homes" standards. 
          Lack of communication with ALL Tenants:  There has been no communication with the residents of Ennerdale House to date - and the consultation starts in two days time.  We got this invite from a resident of Derwent House

          Lack of communication with ALL local residents:  As per usual - EastendHomes' appreciation of the impact that works to the Estate will have on all local residents is absolutely non-existent (but what's new?).  Nobody living in streets affected by the development have received invites.

          Lack of awareness of Site Contamination and remediation required prior to all soft landscaping:  The consultation is to mark the formal opening of the Recipe Tree Garden (aka The Butter Garden).  It would appear that EastendHomes managers and management board have:
          • NOT read the contents of the reports that their architects have commissioned.
          • NOT appreciated the contents of documentation supporting the latest planning conditions submission to Tower Hamlets Council on their behalf PA/10/01093 - Approval of Details - Site Remediation
          • NOT recognised that half a metre of top soil may well have to be removed from all public landscapes area on the Estate due to the presence of widespread contamination. (see Phase III Remediation Strategy)
          Possible site Remediation Measures
          Site Soils: 
          • Confirmation that the entire site area is contaminated and that remedial measures are required to remove risk to all areas of soft landscaping
          • Likely removal of soils within the site to remove thr risk to human health
          • alter the chemical state of the site soils to reduce the impact of the end use soils on the proposed receptors
          Phase 11 Remediation Strategy - Site at Eric and Treby estates (para 2.5 page 8)
          In other words, the garden they are opening/celebrating may well have to be dismantled and soil removed to a depth of at least half a metre in order to remediate existing contamination.

          A couple of good questions to start with during the consultation might be to ask
          • why don't EastendHomes officers read and act on reports? and 
          • why is EastendHome consultation always so poorly organised?
          In the meantime we'll be blogging in future posts about the site contamination and plan for remediation works prior to our formal comments on the application for approval of details to satisfy the planning conditions